Content of the chapter
Title page of project proposal
Project focal areas and operational programs in GEF/SGP formulation
Conception of the project (not more than 1 page)
Project Background (not more than 2 pages):
Information about applicant-organization, co-executors, participants, consultants (not more than 1 page)
Goals, measures, outputs of the project
Workplan
Project Monitoring and Evaluation
Budget
Business-Plan and Market strategy
Project Sustainability
Information campaign
Bank details of Applicant-Organisation
Enclosures

PROJECT PROPOSAL FORMAT
Title page of project proposal

Project title:

Project Number: KYR____________________ _____(fulfil by GEF/SGP office)

Project Executing NGO, Community based Organization, Association:
Name:

Mail address:

Phone no: Fax no:

E-mail address:

Project leader (name and title):

Project's institutional partners (organizations, non-register association and etc.)

Project focal areas and operational programs in GEF/SGP formulation:

(Please choose operational programme that by your opinion fit to your project)

Biodiversity Mitigation of Climate Changes
  Arid and Semi-arid Ecosystems  Removing Barriers to Energy Conservation and Energy Efficiency
  Conservation and Sustainable Use of Biological Diversity Important to Agriculture  Promoting the Adoption of Renewable Energy by Removing Barriers and Reducing Implementation Costs
  Forest Ecosystems  Promoting Environmentally Sustainable Transport
  Mountain Ecosystems  Climate Change as Related to Land Degradation Issues
  Coastal, Marine and Freshwater Ecosystems International Waters
  Biodiversity as Related to Land Degradation Issues  Waterbody Based Programme
  Integrated Ecosystem Management  Integrated Land and Water Multiple Focal Area
   Contaminant Based Programme

Project estimated total budget (in Kyrgyz som and equivalent amount in USA Dollars)

Requested amount from GEF / SGP:


Duration of project:


Stamp, signature, date
up

Conception of the project (not more than 1 page)

Conception of the project is needed to National Coordinator and National Steering Committee to examine does the project's organization status, main idea and its procedure of implementation fit to GEF/SGP and National Country Strategy criteria.
Conception of the project has to shortly contain followings:
- Information about Applicant - Organization (juridical status, experience)
- Formulation of environmental problem and proposals for its solving.
- Describing the project implementation locality and key stakeholders from whose activities depends problem solving or whose interests will be affected
- List of project participants (executors, partners, target groups)
Attention! !
Because filling out the application form demands plenty of time, it is recommended before starting fill out the form get approval of conception from National Coordinator or members of National Steering Committee.

Project Background (not more than 2 pages):

1.Environmantal evaluation.
2. Socio-economic context
3. Institutional/law/policy context
4. Formulation of environmental threats and their causes
5. Reasons of choosing and working out the project: why the project is needed, what it aims to change and how, what will be the global benefits from the project and how it can be measured?
6. Why the project fits to chosen GEF/SGP focal area and operational programme.

Evaluation has to be part of project development process. Evaluation also needs to define influence of implementation outputs of the project to situation. This part also has to contain information about measures concern project goals, implementing or planning by other international, foreign, national projects, programmes, organizations.

Information about applicant-organization, co-executors, participants, consultants (not more than 1 page)
1.Define responsibilities of applicant-organization, co-executors, participants, and consultants
2.Working experience in the project proposal field, implemented projects (title, duration, fundin source).
3.Number of members of organization, its funding sources, premises, facilities, budget for last and current year.
4. Information about measures for involving stakeholders in process of project working out and approval its goals and tasks.
IGoals, measures, outputs of the project. (not more than 2 pages)
Briefly describe, what project is going to change, how situation will change after finishing the project, what exactly local population will do otherwise than now. Describe measures that will be undertaken for reaching these outputs.

§ Common Goal. To ensure global environment benefits in focal area biodiversity, international waters, etc.
§ Project Tasks. Realistic task (tasks) that will be solved after finishing project
§ Expecting outputs. Outputs on each task have to be tangible, concrete, measurable. For-example, so many audiences have been taught in so many seminars, number of livestock or species increased.
§ Indicators. Parameters of change or outputs that show how so far task implemented. For-example, task - built multistory house. Indicator - number of built story.
§ Activity. Measures and activities that need to reach output. Activity has to be concern outputs and budget. Formulation types and stages have to be corresponding to following demands: SMART (Specific, Measurable, Achievable, Realistic…)
§ Assumptions and risks. Possible situation when project activity will be hampered or impossible and this situation doesn't depend on the project. For-example, unkind relation with local authority, pressure from higher structure, changing tax code, fire, flood and etc.

Workplan (not less than 2 pages)
Every project proposal has to contain working plan (logical structure + schedule) that demonstrate coincidence goals, activities, outputs, requested budget and time. Workplan, like a project proposal has to be work out with involving stakeholders of the project to reach understanding and consent on context components of the project and time framework.
Project components Indicators Responsible Assumptions and risks Measures for creating conditions and decreasing risks.
Goal
       
Task        
Output 1        
Type of activity 1.1.        
Type of activity 1.2.        
Type of activity 1.3.        
Output 2        
Type of activity 2.1.
       
Type of activity 2.2.        
Type of activity 2.3.        
Output 3        
Type of activity 3.1.
       
Type of activity 3.2        
Type of activity 3.3        
(This scheme is model, if it needs add lines and table column, use album format)
Project Schedule
Project components Indicators Responsible Budget Duration (quarter, month)
1 2 3 4 5 6 7 8 9 10 11 12
Goal
                             
Task                              
Output 1                              
Type of activity 1.1.                              
Type of activity 1.2.                              
Type of activity 1.3.                              
Output 2                              
Type of activity 2.1.
                             
Type of activity 2.2.                              
Type of activity 2.3.                              
Output 3                              
Type of activity 3.1.
                             
Type of activity 3.2                              
Type of activity 3.3                              
(This scheme is model, if it needs add lines and table column, use album format)
up

2003© ГЭФ Программа малых грантов
e-mail: geflife@elcat.kg ,
тел: 62-57-04, сайт:http://gef.undp.kg

Разработка и поддержка: knir@netmail.kg
Условия для лучшего просмотра: Область экрана - от 600*800;
Internet Explorer (от 4.0) & Netscape Navigator( от 4.7)
Версия на русском